Federal Endangered Species Act

Section 10 (Habitat Conservation Planning)

Digest of Recent Case Law

November, 2002

 

by

Tara L. Mueller, Esq.

Deputy Attorney General

California Office of the Attorney General

Land Law Section, Oakland CA

The views herein expressed are solely those of the author, and do not necessarily reflect the views of the California Attorney General, the California Department of Justice, or any other California state agency.

 

 

 

 

Meaning of Minimize and Mitigate. 1

1.   D.C. Circuit Holds FWS Violates Section 10 in Issuing an ITP for a Housing Project.  Gerber v. Norton, 294 F.3d 173 (D.C. Cir. 2002). 1

2.   Texas District Court Upholds HCP for Development Project Against ESA and NEPA Challenges. Center for Biological Diversity v. U.S. Fish and Wildlife Service, 202 F. Supp. 2d 594 (W.D. Tex. 2002). 4

NEPA Review: 7

1.   Alabama District Court Issues Preliminary Injunction Against Construction Pursuant to Two ITPs Issued Without Environmental Impact Statement.  Sierra Club v. Norton, 207 F. Supp. 2d 1310 (S.D. Ala. 2002). 7

Transferability of Take Permits: 9

1.   the National Marine Fisheries Service issued final regulations authorizing ITPs, safe harbor agreements, and candidate conservation agreements to be transferred to new permittees, provided certain conditions are met.  67 Fed. Reg. 57970 (Sept. 13, 2002). 9

 

Meaning of Minimize and Mitigate

1.       D.C. Circuit Holds FWS Violates Section 10 in Issuing an ITP for a Housing Project.  Gerber v. Norton, 294 F.3d 173 (D.C. Cir. 2002).

 

         Case Summary

 

         Plaintiffs, Defenders of Wildlife and one individual (Defenders), challenged the FWS’ decision to issue an ITP pursuant to section 10 of the ESA.  The ITP authorized the taking of the Delmarva fox squirrel in connection with a proposed residential development project in Maryland.  Plaintiffs argued that the FWS acted arbitrarily and capriciously in issuing the permit because the FWS failed to allow public comment on a key component of the permit application and failed to find that the developer’s proposed alternative would minimize the impacts of the taking to the maximum extent practicable.  The district court granted summary judgment for the FWS, but the D.C. Circuit reversed.

 

         The FWS had published in the Federal Register a notice of availability of the ITP application and accompanying habitat conservation plan (HCP), implementing agreement, and environmental assessment as required by section 10(c) of the ESA, and also had mailed a copy of these documents to Defenders pursuant to a previous stipulation.  However, the documents the FWS made available for public review did not include a map of the proposed mitigation site for the project.  In responding to Defenders’ Freedom of Information Act (FOIA) request for all materials related to the developer’s project and to the conservation of the Delmarva fox squirrel, the FWS indicated that certain documents “were subject to withholding.”  Defenders’ comments on the ITP application noted that it was unable to evaluate the suitability of the proposed mitigation site as fox squirrel habitat (and therefore the impacts of the project on the squirrel) without knowing the precise location of the mitigation site. 

 

         In approving the ITP for the project, the FWS stated that the impacts of the project on the fox squirrel would be mitigated through a permanent conservation easement placed on 31 acres of off-site habitat.  The FWS’ findings also acknowledged that, although the reduced impact alternative would reduce the likelihood of take of fox squirrels, the developer had rejected this alternative because it would involve additional costs and would delay required local government approvals for the project.  The FWS attached a map of the mitigation site to the final HCP.  It rejected Defenders’ request for a thirty day extension of time to comment on the adequacy of the mitigation site.  In their notice of intent to sue, Defenders identified several problems with the adequacy of the mitigation site.

         The court first held that the FWS had violated sections 10(c) and 10(a) of the ESA by failing to make the map of the mitigation site available for public review during the public comment period on the ITP and HCP.  The court noted that section 10(c) expressly provides that “[i]nformation received by the [FWS] as part of any [ITP] application shall be available to the public as a matter of public record at every stage of the proceeding.”  16 U.S.C. § 1539(c).  Although the developer did not physically attach the map to the draft HCP submitted to the FWS, there was no dispute that the map was “received by” the FWS “as part of” the developer’s ITP application.  Accordingly, the FWS was required to make the map available to the public under section 10(c). 

 

         The court held that the FWS also was required to make the map available to the public pursuant to section 10(a), which instructs the FWS to provide an “opportunity for public comment, with respect to the permit application and the related conservation plan.”  16 U.S.C. § 1539(a)(2)(B).  The court held that this opportunity for public comment must be meaningful.  Here, Defenders could not meaningfully comment on the mitigation value of the off-site habitat without knowing the location of the land.  In light of the FWS’ conclusion that the off-site mitigation was necessary for its approval of the ITP, Defenders consequently could not meaningfully comment on the ITP application as a whole without an ability to comment on the site. 

 

         The court rejected the FWS’ assertion that it had in fact made the map available for public comment by making it available for review at the FWS field office, finding no evidence that the map actually was available for public review during the public comment period.  In fact, the court found, the FWS “plainly misled Defenders and other interested members of the public into believing that a map of the mitigation site was not in the public record.”

 

         The court also rejected the FWS’ contention that any failure to make the map available for review was harmless error because it would have reached the same conclusion had it made the map available.  The court held that Defenders had shown that it was prejudiced by its inability to comment on the map by pointing to “at least three serious problems that suggested the site would not provide adequate mitigation for the taking” of the fox squirrel in connection with the project.  The FWS could not overcome this showing of prejudice simply by stating that it was already aware of these problems.  First, the court was not convinced that the agency in fact was aware of these problems, and second, being aware of the problems was not the same as actually considering them.  The court refused to consider the FWS’ self-serving post-hoc assertions that, had it considered Defenders’ comments prior to issuing the permit, it would not have changed its final decision.  The court held that “[w]e do not generally give credence to such post-hoc rationalizations, but rather consider only the regulatory rationale actually offered by the agency during the development of the regulation.”  The court noted that the FWS could easily have avoided protracted litigation by granting Defenders’ reasonable request for a thirty day extension of time to comment on the map.

 

         Finally, the court held that the FWS had violated section 10(a)(2)(B) of the ESA by failing to make an independent finding that the developer would minimize and mitigate the impacts of the project to the maximum extent practicable.  The FWS had acknowledged that the reduced impact alternative would reduce the number of squirrels killed by automobiles by relocating the proposed homes and project access road farther away from the squirrel habitat.  Given this, the FWS could not approve the project as proposed without making a finding that the reduced impact alternative was impracticable.  The court found no evidence in the record that the FWS itself ever made such a finding; instead, it simply repeated the developer’s conclusion the alternative was impracticable because of the developer’s concern that it would entail additional costs and delay. 

 

         The FWS’ decision documents did “not contain any analysis whatsoever as to whether implementation of the reduced impact alternative would actually result in additional costs and delay, or whether the magnitude of such costs or delay would render the alternative impracticable.”  On the contrary, the court noted, the FWS had declared that “no supporting economic analysis was sought or considered.”  The court concluded that the FWS could not satisfy the requirement to make a “maximum extent practicable” finding simply by referencing this provision of the ESA, or by delegating its responsibility to make such a finding to the developer.

 

         Analysis

 

         This case has implications for other ITPs issued by the Services, which commonly approve permits that do not specifically identify the location of proposed mitigation lands.  Under the reasoning of the Gerber case, the Services cannot continue this practice, nor can they withhold information critical to the evaluation of the adequacy of the HCP’s proposed mitigation measures.  The Services also commonly defer to permit applicants’ conclusory assertions of impracticability, notwithstanding the statement in the Services’ HCP Handbook that the applicant must document such statements with actual evidence of economic infeasibility.  The Gerber case requires the Services independently to evaluate such statements based on verifiable information and objective documentation.

 

         2.       Texas District Court Upholds HCP for Development Project Against ESA and NEPA Challenges. Center for Biological Diversity v. U.S. Fish and Wildlife Service, 202 F. Supp. 2d 594 (W.D. Tex. 2002).

 

         Case Summary

 

         Plaintiffs challenged the FWS’ decision to issue an ITP to La Cantera Development Company for the development of a shopping mall.  The ITP authorized La Cantera to take three listed invertebrate species (two beetles and a spider) incidental to the development of their property in exchange for La Cantera’s agreement to dedicate 181 acres of on and off site habitat for these species.  Plaintiffs alleged that the FWS violated section 10 of the ESA because it failed to ensure that La Cantera would minimize and mitigate the impacts of the authorized take to the maximum extent practicable and because it improperly found that the level of authorized take would not jeopardize the continued existence of the species.  In addition, plaintiffs alleged that the FWS violated the National Environmental Policy Act (NEPA) by issuing a finding of no significant impact (FONSI) for the ITP.  The court rejected each of plaintiffs’ claims, and granted summary judgment for the FWS.

 

         The court first held that the FWS did not violate the ESA’s mitigation requirement in failing to require La Cantera to implement a reduced development alternative.  The court reasoned that the FWS had no duty under section 10 to consider alternatives to La Cantera’s project.  Rather, the court agreed with the FWS’s position that its duty under the “maximum extent practicable” requirement is “to analyze the applicant’s proposal to ensure that the impacts of the chosen alternative are minimized and mitigated to the maximum extent practicable.”  Here, plaintiffs had not offered evidence that “the minimization and mitigation measures offered by La Cantera fail to meet the requirements of section 10.”  Moreover, the court stated, even if FWS had a duty to consider alternatives, the FWS did so in this case.  The court also did not agree that the FWS had simply acquiesced to La Cantera’s demands.  Instead, in the court’s view, the FWS had required substantially more mitigation than the company had originally proposed.

 

         The court distinguished Sierra Club v. Babbitt, 15 F. Supp. 2d 1274 (S.D. Ala. 1998), noting that in this case, unlike Sierra Club, there was no evidence that the FWS’ field office was concerned about the inadequacy of the mitigation measures in the developer’s HCP.  In addition, unlike in Sierra Club, the FWS provided an explanation and analysis of why the selected alternative was appropriate, and also found that plaintiff’s alternative was impracticable due in part to the financial impact it would have on the developer.  The court also distinguished National Wildlife Federation v. Babbitt, 128 F. Supp. 2d 1274 (E.D. Cal. 2000), on the basis that, unlike that case, the record in this case showed that the reduced development alternative would in fact have an economic impact on the developer, and the record showed that the developer’s alternative met the criteria for issuance of an ITP.  Therefore, the court held, the FWS did not act arbitrarily or capriciously in issuing and ITP for the developer’s alternative.

 

         The court next held that the FWS was not arbitrary or capricious in failing to require the HCP to meet a recovery standard.  The court, relying on the FWS’ HCP Handbook, found that section 10 does not require an HCP to meet recovery plan goals, but only a “no jeopardy” standard similar to that required of federal agencies under section 7.  The court believed that the HCP met the section 10 “no jeopardy” issuance criterion, even though the HCP relied on acquisition of habitat areas that the FWS admitted were inadequate to ensure species survival, and in regions other than where the development was proposed, contrary to the recovery plan standards for the species.  As to the location and size of the preserves, the FWS appropriately relied on the applicant’s statement that it was “limited by land that was practicably available for sale” during HCP preparation.  The court also upheld the FWS’ reliance on the fact that much of the land surrounding the admittedly inadequate mitigation areas was still in open space and “may become available for preservation in the future.”

 

         The court also rejected plaintiffs’ argument that the FWS violated NEPA in failing to prepare an environmental impact statement (EIS).  Plaintiffs contended that the FWS ignored six of the ten NEPA regulations criteria for preparation of an EIS: the project (1) is in an ecologically critical area; (2) has controversial impacts and unknown risks; (3) is precedential in nature; (4) will have significant cumulative impacts; (5) will result in the destruction of significant scientific resources; and (6) will have an adverse effect on endangered species.  The court rejected each of these assertions, finding that plaintiffs had failed to substantiate their claim and/or that the FWS had adequately considered these issues and had appropriately concluded that the HCP fully mitigated all of the project’s potentially significant environmental effects.

 

         The court rejected plaintiffs’ argument with respect to the “controversial impacts” criterion because it did not believe the dispute to be “substantial” enough in terms of the number and strength of the opposition to the HCP.  The court distinguished other cases in which the courts found a controversy sufficient to require preparation of an EIS on the ground that there were numerous environmentalists and experts who disagreed with the agency’s conclusion not to prepare an EIS.  Here, the court found, the opposition did not rise to the same level, because only one expert disagreed with the FWS’ findings and only two commentators stated that an EIS should be prepared for the project, and “NEPA . . . does not demand scientific unanimity to support a FONSI.”  Therefore, the court held, it could not conclude that the FWS acted in an arbitrary and capricious manner in determining that the comments did not create a sufficient controversy.

 

         The court also disagreed that the HCP and ITP would set an adverse precedent.   Even though the FWS acknowledged that the ITP would establish a precedent for the level of mitigation required in future ITPs for the affected invertebrate species in that county, the FWS found that the ITP was “not dissimilar” for ITPs previously issued in other counties for the same species.

 

         With regard to cumulative impacts, the court held that the FWS’ finding that the authorized development “would add to the overall demand for water resources and increase the burden” to provide water without jeopardizing listed species in the region “does not amount to a finding of significance which would require an EIS.”  Moreover, the plaintiffs had not pointed to anything in the record which described exactly how the FWS’ decision making was flawed.

 

         Finally, the court disagreed with plaintiffs’ assertion that the HCP and ITP by definition would adversely affect listed species, requiring preparation of an EIS.  The court stated that the record supported the FWS’ assertion that it assessed the degree to which the ground beetles and spider would be adversely affected and determined that there would be no significant impact because of the mitigation measures in the HCP. Furthermore, plaintiffs again had not pointed to anything in the record that showed the FWS decision was arbitrary and capricious.

 

         Analysis

 

         This case is significant because, in contrast to the D.C. Circuit’s approach in Gerber v. Norton, the court appears to take developer’s assertions of economic infeasibility simply at face value, and it upholds the FWS’ practice of issuing ITPs that impede species recovery on grounds that greater mitigation would be impractical.  If adopted by other courts, the holding in the Center for Biological Diversity case could make it substantially more difficult to challenge an HCP and accompanying ITP.  This difficulty is underscored by the high degree of deference the court accorded to the FWS’ analysis and conclusions.  The court simply accepted, without questioning, the FWS’ rationale, deferring to the agency’s conclusory analysis, without determining whether that analysis was supported by any evidence in the record, or made logical sense.

 

         The court’s reasoning on the NEPA issue also contrasts with the decision in Sierra Club v. Babbitt, wherein the Alabama District court held that the FWS unlawfully relied on a finding of no significant impact for an HCP and ITP when it did not even know the minimum viable population of the species.  It therefore could not reasonably estimate the extent of the project’s impacts on the species.  Similarly, in this case, the FWS admitted that it did not possess basic information about the invertebrate populations in question, such as the precise location and extent of the species’ range.

 

         In NWF v. Babbitt, a California District Court relied on many of the factors considered by the Center for Biological Diversity court but reached the opposite conclusion.  The NWF court held that the existence of controversy regarding the HCP and ITP, the unique geographical characteristics of the region, the precedential nature of the permit, and the degree to which the permit may affect endangered and threatened species, all counseled in favor of preparing an EIS.  The NWF court held that, while the HCP’s mitigation measures were relevant to the determination whether to prepare an EIS, substantial uncertainty regarding the measures’ potential success required an EIS.  Likewise, in Center for Biological Diversity, the record established significant uncertainty regarding the likely success of the HCP’s mitigation measures, yet the court nevertheless relied on those measures to hold than no EIS was required.

 

NEPA Review:   

1.       Alabama District Court Issues Preliminary Injunction Against Construction Pursuant to Two ITPs Issued Without Environmental Impact Statement.  Sierra Club v. Norton, 207 F. Supp. 2d 1310 (S.D. Ala. 2002).

 

         This court granted plaintiff Sierra Club’s motion for preliminary injunction in a case challenging the FWS’ issuance of two ITPs authorizing take of the Alabama beach mouse.  Plaintiff alleged that the FWS violated NEPA in issuing the ITPs for several high rise condominium towers without first preparing an EIS.  The court held that plaintiff was very likely to succeed on the merits of its claim that the FWS violated NEPA in issuing a FONSI due to the lack of concrete data regarding the effect of habitat loss on the species’ ability to survive and recover, and the minimum habitat requirements necessary for its continued survival and recovery.

 

         In an earlier case, the same court had invalidated two other ITPs issued by the FWS on the ground that the FWS had violated NEPA in preparing a FONSI on the permits.  Sierra Club v. Babbitt, 15 F. Supp. 2d 1274 (S.D. Ala. 1998).  The court held that the lack of: current, reliable population data; information on the distribution of the beach mouse within its range; and an estimate of the minimum viable population size rendered the FONSI arbitrary and capricious.  The court found that, absent this information, the FWS had no basis for determining how the proposed action would affect the beach mouse’s ability to survive and recover. 

 

         In this case, the FWS acknowledged that it did not have the information on beach mouse population density and distribution that the court had found lacking the prior case.  Nevertheless, the FWS asserted that it had avoided the problems with the prior ITPs by using a habitat-based analysis.  The court disagreed, finding that “the record does not demonstrate that the agency has any clearer idea what effect the project will have on the beach mouse under this approach than it did under the incomplete population-based approach previously criticized by the court.”

 

         In reaching its holding, the court first stated that proposed action need not involve a threat of extinction to a federally listed species in order to have a potentially significant effect.  However, the possibility of extinction or extirpation from a traditional habitat weighs heavily in favor of a finding of significance, as does the existence of uncertainty regarding an action’s environmental effects.  In this case, the court held, the destruction of 20% of the “optimal habitat” for the beach mouse, a species listed as endangered due to historic habitat loss, on top of cumulative post-listing losses of an additional 20% of optimal habitat, would have a “significant” impact under any reasonable definition of that term.  The court also held that lack of information about how the loss of this amount of optimal habitat would affect the species also weighed in favor of preparation of an EIS.  The court noted that almost all the post-listing habitat loss was due to the FWS’ issuance of ITPs, for which the agency had never prepared an EIS.  Thus, the FWS could not rely on a prior EIS to supply missing information about the impacts of the ITPs on the beach mouse. 

 

         The court rejected the FWS’ argument that the ITPs in question would only affect the local population and would not affect the species as a whole, finding that local extirpation can still be a significant impact, and that the beach mouse required several discrete but connected colonies to survive.  The FWS had not addressed the effects of habitat fragmentation, barriers to migration along the shoreline and between shoreline and interior habitat, and the effect of increased flooding of interior habitat caused by increased development in the area. 

 

         The FWS also had not addressed how much contiguous habitat would remain after development of the high rise condominiums, nor did it have reliable data on the minimum habitat requirements for a viable beach mouse colony, or the minimum population requirements for long-term survival and recovery of the beach mouse as a whole.  The court dismissed the argument that the ITPs would not have a significant impact because they would “leave slightly more habitat than the lowest estimate of minimum habitat requirements,” finding that significant impacts include impacts to species recovery as well as survival, and impacts to a species’ maximum supportable population size.  Moreover, because the remaining habitat would be at or below the FWS’ only general estimate of minimum habitat, the court found the agency’s finding of insignificance insupportable in the absence of a reasonably reliable means for analyzing the significance of the impact of such habitat loss on the beach mouse’s viability and recovery.

 

         The court also dismissed the argument that any significant impacts were mitigated to insignificance by the HCP accompanying the ITPs, concluding that while the mitigation measures were “admittedly beneficial” and minimized many of the lesser adverse effects of the action, they did “nothing to lessen the irreducible destruction of habitat.”  The court stated that even if it were to presume that the HCP would completely reduce any effect on the habitat set-aside to insignificance, the HCP would not undo the habitat destruction caused by construction of the condominiums, and would not create new habitat to replace that lost through construction.

 

         The court further found that the lack of information regarding the impact of such construction and the loss of optimal habitat on the beach mouse militated in favor of preparation of an EIS.  The court observed that, given the lack of fundamental information on the effects of habitat loss, “any alleged ‘finding’ that the project will not significantly affect the species is the purest sophistry.”  The court rejected the argument that the FWS was not required to prepare an EIS unless it found that the ITPs would jeopardize the species.  The court stated that this would turn NEPA’s requirement of informed decision making on its head, “making ignorance into a powerful factor in favor of immediate action where the agency lacks sufficient data to conclusively show not only that the proposed action would harm an endangered species, but that the harm would prove to be ‘significant’.”  The regulations cited by the defendants were inapposite because they addressed the FWS’ duties with regard to issuance of ITPs under the ESA, not its duties under NEPA.

 

         Having found that plaintiff was likely to succeed on the merits of its claim that an EIS was required, the court then determined whether a preliminary injunction was warranted.  The court concluded that, under NEPA, it was required to balance the equities in determining whether to grant an injunction.  It rejected plaintiff’s contention that the U.S. Supreme Court’s decision in Tennessee Valley Authority v. Hill, 437 U.S. 153 (1978) precluded such balancing.  The court then found that the balance of harms strongly favored an injunction.  The threatened destruction of optimal habitat would be irreversible, the failure to prepare an EIS constituted an irreparable procedural injury, and a preliminary injunction was necessary in order to preserve the court’s ability to award meaningful and effective relief.  Further, the economic harm to the developers did not outweigh the irreparable harm caused by failure to prepare an EIS, and the public interest favored informed agency decision making and protection of endangered species.

 

         Analysis

 

         This represents one of those rare cases where the court truly understood the significant biological implications of direct and cumulative loss of habitat of a listed species.  The court also recognized that habitat set asides alone cannot mitigate the effects of such loss, because there is always a net loss of suitable habitat under such arrangements.  Finally, this decision reaffirms the importance of informed decision making under NEPA.  The court justifiably resisted the temptation to turn NEPA into a paper tiger by allowing the projects to proceed without adequate environmental analysis before irreversible impacts occur.  The court’s analysis in this case stands in sharp contrast to the analysis of the District Court for the Western District of Texas in Center for Biological Diversity v. Norton, 2002 WL 1160598 (W.D. Tex. 2002) (summarized above).

 

Transferability of Take Permits:

1.       the National Marine Fisheries Service issued final regulations authorizing ITPs, safe harbor agreements, and candidate conservation agreements to be transferred to new permittees, provided certain conditions are met.  67 Fed. Reg. 57970 (Sept. 13, 2002).